- 1991 Qualified as Millwright
- 2001 Registered as Installation Electrician - DOL Registration
- 2003 Registered as Master Installation Electrician - DOL Registration
- 2012 Earthing & Lightning Protection Course
GE Kusile Power Station Projects Elec, C&I, Mech, Piping & HVAC 2018 - Current
GE Kusile Power Station Projects Installation of Betabars (Unit 5 - 6) Elec 2019
Wet Flue Gas Desulfurization (WFGD) Completion and rectification works Elec 2019 - Current
Boiler Feedwater Pump Cartidge Replacement and Vorecon alignment (Unit 5 - 6)
HVAC E & I Installation - Turbine Building (Unit 5 - 6) Elec 2021 - Current
C & I Installation Turbine (Unit 5 - 6) C & I 2022 - Current
ACC Completion and Rectification Works (Unit 5 - 6) Elec, C&I 2022 - Current
GE (Kendal Power Station) High Frequency Transformer replacements on Precipitator (Unit 1 - 4)Mech, Elec 2021 - Current
GE (Lethabo Power Station) High Frequench Transformer replacements on Precipitator (Unit 1,4 & 6) Mech 2022 - Current
Bushveld Minerals (Vanchem Plant) E & I Installation WDF E & I 2021
Chemical plant upgrade (Turnkey) Mech, Piping, Elec, C & I 2021 - 2022
RSV Minerals - Two Rivers Platinum E & I Early works Merensky Shaft Project E & I Current
11kV Overhead Line Tie - ins Elec Rolls Royce Solutions Africa 2.5mVA (11kV) Genset Installation Mech & Elec Current 11kV Overhead Line Tie - ins Elec
Dwarsrivier Chrome Mine (Neda Engineering Group) Stacker Project Elec 2021 - 2022
ENZA Construction Middelburg Provincial Hospital Project Elec Current
VEA (South 32 Wesselsmine - Hotazel) Underground Secondary Plant Upgrade Elec 2019
Please make sure you complete all the fields below to be able to submit a review.